|
TESTIMONY OF THE HONORABLE H. WILLIAM DeWEESE
MAJORITY LEADER, PENNSYLVANIA HOUSE OF REPRESENTATIVES
Before the United States House of Representatives Committee on Oversight and
Government Reform Subcommittee on Domestic Policy on Federal Electric
Transmission Corridors:
Consequences For Public And Private Property.
April 25, 2007
Good afternoon Mr. Chairman and members of the Committee on Oversight and
Government Reform's Subcommittee on Domestic Policy.
Mr. Chairman, I am H. William DeWeese. I appreciate the opportunity to appear
before you and Members of the Sub-Committee on Domestic Policy to provide
comment on the implementation of Section 1221 of the Energy Policy Act of 2005.
I respectfully offer these comments in my capacity as the Majority Leader of the
Pennsylvania House of Representatives and as the duly elected State Legislator
for the 50th Legislative District, which encompasses all of Greene County and
parts of Washington and Fayette Counties.
My testimony, in large part, will consider the impact section 1221 will have on
the Commonwealth of Pennsylvania, its people and political subdivisions.
Accordingly, it is my belief that section 1221 as public policy will, if
implemented, advance an element of the Energy Policy Act of 2005 which is void
of public benefit, which ignores environmentally clean, renewable,
energy-efficient and cost-effective alternatives, and which forsakes the rights
of states and their political subdivisions to adopt, administer, and manage land
use policies and decisions that conflict with the ambitions of profit seeking
corporations seeking to locate and construct high voltage transmission lines.
Section 1221 gives the Secretary of Energy the authority, based on congestion
studies, to designate national interest electric transmission corridors in any
geographic area of the United States that is experiencing electric transmission
capacity constraints or congestion. Furthermore, section 1221 gives the Federal
Energy Regulatory Commission (the FERC) "backstop" authority to issue one or
more permits to construct a transmission line in a Department of Energy
designated national interest energy transmission corridor, if specific
conditions exist. For instance, if the Pennsylvania Public Utility Commission
(PA PUC) would fail to approve a transmission line siting application for more
than one year following the filing of the application seeking approval to locate
or construct a high voltage transmission line or one year after the designation
of the relevant national interest electric transmission corridor, whichever is
later; OR if the PA PUC would condition its approval in such a manner that the
proposed transmission line would not significantly reduce transmission
congestion; OR would not be economically feasible, the FERC could use its
Federal eminent domain power to locate and construct the transmission line in
Pennsylvania, regardless of the findings of the PA PUC or any other state
administrative agency that is statutorily charged with assuring that the high
voltage transmission line is in the public interest and will provide a public
benefit.
The PA PUC is the administrative agency of the Commonwealth statutorily
empowered with jurisdictional authority over the rates, terms, and conditions of
retail electric utilities. Moreover, it is the duty of the PA PUC pursuant to
statute to, among other things, assure that the rates of public utility service,
including electric service, are just and reasonable; that there is no
discrimination in rates; and that public utility service is safe and reliable.
The PA PUC also has regulatory authority over the review and approval of
applications to locate and construct transmission lines. Additionally, the
Office of Consumer Advocate was established in 1976 and the Office of Small
Business Advocate in 1988 for the explicit purposes of representing the interest
of consumers and small businesses, respectfully, in any matter or proceeding
properly before the PA PUC, including matters relating to the location and
construction of high voltage transmission lines. I submit that if the Department
of Energy designates a national interest energy transmission corridor in
Pennsylvania with little or no consultation and coordination with all
administrative agencies charged with representing the rights and interest of
ratepayers and assuring a public benefit, it would be difficult if not
impossible to conclude that the project would be in the public interest.
The accompanying backstop authority conveyed to the FERC could diminish or even
eliminate the roles of the PA PUC, the Offices of Consumer and Small Business
Advocates, and other administrative agencies that were established for the
express purpose of protecting Pennsylvania’s natural, historical, cultural,
and recreational resources and, in some cases, reviewing and commenting on
transmission line siting applications. These agencies include the Pennsylvania
Department of Environmental Protection, the Department of Conservation and
Natural Resources, the Department of Transportation, the Game Commission, and
the Historical and Museum Commission.
If the FERC is permitted to use its congressionally conveyed authority to
commandeer and usurp the traditional role of states and their administrative
agencies to review and approve the location and construction of high voltage
transmission lines, Pennsylvania, not unlike every other state, would have no
control, no say, and no recourse other than expensive litigation; over
transmission planning, location, and construction within its geographic borders.
However, there is a remedy; the repeal of section 1221 of the Energy Policy Act
of 2005. I submit that without repeal, implementation of section 1221 could be
viewed as one of several acts in a national drama choreographed to alter
fundamentally our form of Government in the name of "national security."
It is important for you to know that my colleagues and I in the Pennsylvania
General Assembly may face the reality of and be forced to address the issues
radiating from Congressional enactment of section 1221 sooner than most. The
fact is that on March 6, 2006, both Allegheny Power and the PJM Interconnection
submitted an interstate high voltage transmission line project to the Department
of Energy for early designation as a national interest electric transmission
corridor. This project, known as the Trans-Allegheny Interstate Line or TrAIL
project, proposes to locate and construct a 240-mile, 500 kilovolt interstate
transmission line; 40 miles of which will extend from Washington County and
traverse parts of my 50th Legislative District in Greene County. From Greene
County, the remaining miles of the proposed line would snake through parts of
West Virginia and terminate in Northern Virginia.
On Friday, April 13, 2007, Allegheny Power, the jurisdictional electric
distribution company that serves most of Southwestern Pennsylvania, filed the
TrAIL project application with the PA PUC. At this point, review and approval of
the TrAIL project is subject to PA PUC regulations. However, and although the
Department of Energy has delayed action on requests for early designations of
national interest electric transmission corridors, Allegheny Power and the PJM,
singular or in combination, could deal their corridor designation requests into
play, if the PA PUC would fail to approve the TrAIL project.
The PJM has also requested national interest electric transmission corridor
designation of another high voltage interstate transmission line project
promoted by American Electric Power (AEP), Allegheny Power, and Pepco. This
project involves the location and construction of an approximately 550-mile, 765
kilovolt transmission line that would extend from the panhandle region of West
Virginia, traverse Pennsylvania and Maryland and end in New Jersey.
If national interest energy transmission corridor designations would be granted
to both projects, a Piedmont Environmental Council review of early designation
requests revealed that land in approximately 50 of Pennsylvania's 67 counties
has the potential of becoming subject to federal eminent domain authority.
There is no doubt that the granting of national interest electric transmission
corridors in Pennsylvania and the siting and construction of high voltage
transmission lines of the magnitude proposed by Allegheny Power, AEP, and the
PJM would have significant negative outcomes for the Commonwealth of
Pennsylvania, its people and political subdivisions. The following is a mere
snapshot of Pennsylvania's economic, cultural, historical, natural, and scenic
resources whose sustainability could be jeopardized by corridor designations:
(1) As of April 13, 2006, 323,366 acres of farmland had been preserved in 53
counties under the Commonwealth's agricultural land preservation programs.
(2) Pennsylvania has 120 state parks on 283,000 acres, 20 state forests on 2.1
million acres of forestland in 48 of 67 counties, and 300 state game lands on
1.4 million acres. Pennsylvania's state forestland is one of the largest
expanses of public forestland in the eastern United States.
(3) Allegheny National Forest (500,000 acres), Delaware Water Gap National
Recreational Area (70,000 acres), Gettysburg National Military Park
(6,000acres), Valley Forge National Park (4,000 acres) and Fort Necessity
National Battlefield (900 acres).
(4) Forty-two places in Pennsylvania are listed on the National Register of
Historic Places.
Implementation of section 1221 would have a devastating impact not only on my
constituents in Southwestern Pennsylvania, but also on people across the
Commonwealth who may soon discover that their homes, children's schools,
businesses, and workplaces could be situated in or near a proposed corridor. The
likelihood of this inevitability juxtaposed with the possibility that my
constituents and other Pennsylvanians may face increased electric rates but
receive no economic or quality-of-life benefit from interstate transmission line
projects, could face the possibility of losing their homes through condemnation
and living in fear of chronic or terminal health outcomes, makes the rationale
for enacting a profit driven public policy in the name of national security
difficult to understand.
As I relayed previously, section 1221 is void of public benefit, ignores
environmentally clean, renewable, energy-efficient and cost-effective
alternatives, and sacrifices the traditional power of states to adopt,
administer, and manage land use policies and decisions, especially if a decision
would conflict with the ambitions of profit motivated corporations seeking to
locate and construct high voltage transmission lines. There are alternatives to
high voltage transmission lines. However, our failure to require consistent
investment in alternative energy has us here today discussing what may become
another failed national energy policy. Gasoline prices continue to rise at
alarming rates; we remain dependent on foreign oil; and whether or not there
will be adequate investment in conservation, renewable and alternative energy
remains elusive. It is clear that we can not continue on this road of energy
uncertainty. However, and as I have stated before, the lives of my constituents
and the people of the Commonwealth of Pennsylvania should not be disrupted
because of an energy policy that ignores their quality of life for the benefit
of profit driven corporations. There is no doubt in my mind that section 1221 of
the Energy Policy Act should be repealed posthaste. With that I will continue to
oppose efforts to designate national interest electric transmission corridors
and any projects seeking to locate and construct interstate high voltage
transmission lines in the Commonwealth of Pennsylvania.
I thank you for your consideration of my comments and your willingness to
consider the consequences section 1221, if implemented, would have on state
sovereignty and the lives of people nationwide.
|